HIGH PASS-RATE CDCS–100% FREE UNLIMITED EXAM PRACTICE | CDCS EXAM TOPICS

High Pass-Rate CDCS–100% Free Unlimited Exam Practice | CDCS Exam Topics

High Pass-Rate CDCS–100% Free Unlimited Exam Practice | CDCS Exam Topics

Blog Article

Tags: Unlimited CDCS Exam Practice, CDCS Exam Topics, CDCS New Exam Bootcamp, Reliable CDCS Test Questions, CDCS Valid Exam Test

If you are worried about your CDCS real exam and you are not prepared so, now you don't need to take any stress about it. Get most updated EXIN dumps torrent with 100% accurate answers. Our website is considered one of the best website where you can save extra money by getting one-year of free updates after buying the CDCS Dumps PDF files.

EXIN CDCS Exam Syllabus Topics:

TopicDetails
Topic 1
  • Data Centre Life Cycle and Standards: This section of the exam measures the skills of data center professionals and covers the various stages involved in the life cycle of a data center, from planning and design to implementation and decommissioning.
Topic 2
  • Data Centre Environmental Considerations and Efficiency: This section evaluates the proficiency of data center professionals in addressing environmental factors and promoting efficiency within data center operations. The target audience, including data center managers and engineers, will be tested on their ability to identify and implement measures that enhance energy efficiency, cooling management, and sustainable practices.
Topic 3
  • Designing and Implementing a Data Centre: In this module, the exam assesses the knowledge of Exin data center professionals tasked with the design and implementation of data centers. Candidates will learn the key principles of creating an efficient data center layout, including considerations for scalability, redundancy, and security.

>> Unlimited CDCS Exam Practice <<

Pass Guaranteed Quiz 2025 Trustable EXIN Unlimited CDCS Exam Practice

Annual test syllabus is essential to predicate the real CDCS questions. So you must have a whole understanding of the test syllabus. After all, you do not know the CDCS exam clearly. It must be difficult for you to prepare the CDCS exam. Then our study materials can give you some guidance. All questions on our CDCS study materials are strictly in accordance with the knowledge points on newest test syllabus. Also, our experts are capable of predicating the difficult knowledge parts of the CDCS Exam according to the test syllabus. We have tried our best to simply the difficult questions. In order to help you memorize the CDCS study materials better, we have detailed explanations of the difficult questions such as illustration, charts and referring website. Every year some knowledge is reoccurring over and over. You must ensure that you master them completely.

EXIN EPI Certified Data Centre Specialist Sample Questions (Q57-Q62):

NEW QUESTION # 57
When installing a raised floor, can we use a spirit level bar to level the floor?

  • A. Yes, but spirit level bars can only be used in the vertical plane.
  • B. Yes, spirit level bars can be used as long as their length is longer than 60 cm/2 ft (the size of a typical raised floor tile).
  • C. No, because using a spirit level bar, a measurement error will be transferred from pedestal to pedestal.
  • D. Yes, using a spirit level bar for raised floors higher than 40 cm is preferred.

Answer: C

Explanation:
A spirit level bar should not be used for leveling a raised floor, as measurement errors are likely to propagate from one pedestal to the next. Spirit levels can introduce cumulative errors, leading to uneven floors, particularly in large installations where precise leveling is critical.
Detailed Explanation:
Using a laser level or a precision leveling device is recommended to ensure accuracy across all floor tiles. Spirit levels, while adequate for short spans, can transfer small inaccuracies from one pedestal to another, which can cause alignment issues and floor instability over time.
EPI Data Center Specialist References:
EPI data center guidelines discourage the use of spirit levels for raised floors. Instead, they advocate for precision tools like laser levels that ensure consistency and accuracy in large-scale installations, aligning with best practices for raised floor construction.


NEW QUESTION # 58
The computer room has high levels of H2S gas contamination. What is the best option to resolve this issue?

  • A. Install air-scrubbers.
  • B. Vacuum the whole room using a HEPA/S-Class-based filter.
  • C. Provide more air changes per hour by adding more fresh air to the computer room.
  • D. Clean the room and racks with a damp/wet cloth.

Answer: A

Explanation:
High levels of H2S (hydrogen sulfide) gas contamination in a computer room are best addressed by installing air-scrubbers. Air-scrubbers can effectively filter out contaminants, including corrosive gases like H2S, ensuring clean air circulation and protecting sensitive IT equipment from potential corrosion and damage.
Detailed Explanation:
Air-scrubbers are designed to remove various airborne contaminants and are particularly useful in environments where corrosive gases are present. These systems use filters or chemical reactions to neutralize harmful substances, making them ideal for data centers that need to maintain high air quality for equipment reliability.
EPI Data Center Specialist References:
EPI guidelines suggest air-scrubbing technologies to remove contaminants that pose risks to electronic equipment, maintaining air quality and reducing corrosion risk.


NEW QUESTION # 59
You are working with a customer who requires a guarantee that THDi levels coming from the UPS should not exceed more than 3% THDi. Furthermore, he wants to run a power-efficient data center. The UPS has a 6-Pulse SCR/Thyristor based rectifier. The current load on the UPS is approximately 80%. The customer indicates they are not expecting any changes on the ICT infrastructure for the next 3 years.
What should you recommend?

  • A. Nothing, the UPS will be able to take care of the right levels of THDi
  • B. Install a passive harmonic filter on the UPS
  • C. Install an isolation transformer rated at K13 or K20
  • D. Install an active harmonic filter on the UPS

Answer: D

Explanation:
Given the customer's requirement to limit Total Harmonic Distortion (THDi) to below 3% and the presence of a 6-pulse SCR/Thyristor-based rectifier, an active harmonic filter is the best solution. A 6-pulse rectifier typically generates higher harmonic distortion, often exceeding 3%, especially under substantial loads like 80%. An active harmonic filter dynamically monitors and compensates for harmonic distortion, effectively reducing THDi and supporting a more power-efficient operation, aligning with the customer's energy efficiency goals.
Detailed Explanation:
Passive harmonic filters can reduce harmonics but are less effective at maintaining low THDi levels under varying loads. Active filters offer real-time correction and can achieve lower THDi levels than passive filters, especially in systems with fluctuating loads or where strict harmonic limits are required. Installing an active harmonic filter will ensure compliance with the specified THDi limits and optimize power quality.
EPI Data Center Specialist References:
EPI guidance on power quality management recommends active harmonic filters for environments where strict THDi levels are necessary. Active filters offer better control over harmonic levels, supporting both compliance and operational efficiency.


NEW QUESTION # 60
A computer room with a raised floor has been designed with racks in a hot/cold aisle setup.
What should you recommend for the placement of down-flow air conditioners?

  • A. Air conditioners should always be placed at both sides of each row of racks
  • B. Air conditioners perpendicular to (at the end of the row of) the Cold-Aisle
  • C. Air conditioner placement has no influence on cooling effectiveness and efficiency. Hence, they can be placed at any convenient location.
  • D. Air conditioners perpendicular to (at the end of the row of) the Hot-Aisle

Answer: B

Explanation:
In a hot/cold aisle configuration, placing down-flow air conditioners perpendicular to the cold aisle ensures that cool air is directed efficiently into the cold aisles where server intakes are located. This layout allows for optimal cooling performance by aligning the airflow directly with the equipment intakes, minimizing hot spots and enhancing cooling efficiency.
Detailed Explanation:
With a raised floor design, cold air from the air conditioners is supplied into the cold aisle, where server intakes are located. Positioning the air conditioning units perpendicular to the cold aisles ensures that cool air is delivered directly into these aisles, preventing air mixing and optimizing cooling. This setup takes full advantage of the airflow management strategy inherent to the hot/cold aisle configuration.
EPI Data Center Specialist References:
EPI guidelines on cooling emphasize that down-flow air conditioners should be positioned to maximize the effectiveness of cold aisle delivery, which improves cooling efficiency and helps maintain consistent temperatures across server racks.


NEW QUESTION # 61
You are allowed to use a calculator for this question.
A computer room has a net volume of approximately 2,500 m³ / 88,287 ft³.
The temperature is 20 °C / 68 °F.
The required design concentration is 7%.
The S-Factor is 0.1359 (metric) / 1.885 (imperial).
Calculate the amount of gas required for this computer room based on FM200. What is the correct weight?

  • A. Approximately 820 kg / 1,800 lbs
  • B. Approximately 1,640 kg / 3,600 lbs
  • C. Approximately 410 kg / 900 lbs
  • D. Approximately 1,390 kg / 3,000 lbs

Answer: A

Explanation:
The amount of FM200 gas required can be calculated using the formula:
Weight of Gas=Net Volume×Design Concentration×S-Factortext{Weight of Gas} = text{Net Volume} times text{Design Concentration} times text{S-Factor}Weight of Gas=Net Volume×Design Concentration×S-Factor Using metric units:
Net Volume: 2,500 m³
Design Concentration: 7% (or 0.07)
S-Factor: 0.1359
Calculation:
2,500 m3×0.07×0.1359=821.325 kg2,500 , text{m}